Operational Risks
Operational risks relate to flight operations, regulatory compliance, and field conditions.
O1: ANAC BVLOS Approval Delays
Level: High
Description
Beyond Visual Line of Sight (BVLOS) operations require ANAC authorization under Resolution 550/2025. Regulatory approval timelines are uncertain and may delay operational readiness.
Mitigation
- Aerotec leadership: Regulatory relationship is Aerotec's domain
- Early application: Submit authorization requests immediately
- Parallel development: Platform development independent of flight ops
- VLOS interim: Limited operations within visual range during approval
Contingency
- Develop and test platform with simulated/historical data
- Phase 1-2 can proceed without active flight operations
- Adjust timeline expectations if approval delayed
O2: Weather and Environmental Conditions
Level: Medium
Description
Vaca Muerta's desert environment presents operational challenges:
- High winds: Frequent dust storms and sustained winds
- Extreme temperatures: Hot summers, cold winters
- Dust: Sensor contamination and visibility reduction
- Limited shelter: Remote sites lack infrastructure
Mitigation
- Weather monitoring: Automated flight hold during adverse conditions
- Equipment ratings: Hardware rated for environmental conditions
- Maintenance protocols: Regular cleaning and calibration
- Redundant sensors: Multiple data sources reduce single-point failures
Contingency
- Conservative flight windows during extreme weather seasons
- Indoor/protected sensor deployments where feasible
- Manual inspection backup during extended weather events
O3: Remote Site Connectivity
Level: Medium
Description
Vaca Muerta's remote locations have limited connectivity infrastructure:
- Satellite dependency: Primary connectivity for many sites
- Bandwidth limitations: Large data uploads challenging
- Latency: Satellite latency impacts real-time capabilities
- Reliability: Weather and equipment affect uptime
Mitigation
- Data compression: Optimize upload sizes
- Prioritization: Critical alerts before full data
- Store-and-forward: Queue uploads during outages
- Redundant connectivity: Multiple paths where available
Contingency
- Extended SLA for sites with connectivity challenges
- Local processing for immediate alerts
- Scheduled uploads during connectivity windows
O4: 24/7 Coverage Sustainability
Level: Medium
Description
Continuous 24/7 autonomous operations require sustained reliability:
- Aircraft availability: Maintenance, battery cycles
- Dock reliability: Charging, weather protection
- Staff coverage: Monitoring and response around the clock
Mitigation
- Redundant fleet: Spare aircraft per site
- Preventive maintenance: Scheduled servicing
- Monitoring systems: Health alerts before failures
- Shift planning: Adequate RTIC staffing
Contingency
- Reduced coverage during maintenance windows
- Manual inspection backup
- Prioritized site coverage during equipment issues