Phase 4: MVP Hardening
Duration: Months 6-9 Goal: "Production-ready, audit-ready"
Overview
Phase 4 prepares the platform for production operations with dashboards, reporting, enterprise integration, and comprehensive documentation for audit compliance.
Deliverables
| Deliverable | Description |
|---|---|
| RTIC Dashboards | Production dashboards deployed to control room |
| SAP PM Integration | Bidirectional work order integration |
| Reporting Package | Automated reports for compliance and operations |
| Data Governance | Retention policies, access controls, audit logs |
| Knowledge Transfer | Comprehensive documentation and training |
Success Criteria
- All 17 use cases at ≥95% accuracy
- Dashboards deployed to RTIC
- SAP PM integration operational (or deferred with agreement)
- SLA compliance demonstrated
- Knowledge transfer complete
- Operational runbooks delivered
Key Activities
Week 1-6: Production Deployment
- Dashboard development and deployment
- SAP PM connector implementation
- Performance optimization
- Security hardening
Week 7-12: Handover & Documentation
- Operator training sessions
- Documentation completion
- Operational runbook creation
- Support transition planning