RACI Matrix

Responsibility assignment matrix for the YPF Unmanned Aerial Monitoring Service.

Legend: R=Responsible, A=Accountable, C=Consulted, I=Informed

MVP Phases (Months 0-9)

Flight Operations

ActivityAerotec OpsTrifork AITrifork PMYPF
Mission PlanningR/AIIC
Flight ExecutionR/AIII
Emergency ResponseR/ACII
Equipment MaintenanceR/AIII
ANAC ComplianceR/AIII

AI Platform Development

ActivityAerotec OpsTrifork AITrifork PMYPF
Data Ingestion PipelineCR/AII
AI Model DevelopmentIR/ACI
Dashboard DevelopmentIRAC
Multi-Sensor CorrelationIR/ACI
Accuracy OptimizationCR/AIC

Integration

ActivityAerotec OpsTrifork AITrifork PMYPF
FlightHub 2 IntegrationCR/AII
SAP PM IntegrationCRAR/A
RTIC Dashboard DeploymentRCAR
Genetec Security IntegrationCRAC

Project Management

ActivityAerotec OpsTrifork AITrifork PMYPF
Sprint PlanningCCR/AI
Progress ReportingCCR/AI
Risk ManagementCCR/AC
Milestone AcceptanceCCRA
Knowledge TransferIRAC

Post-MVP Operations (Months 9-48)

Ongoing Operations

ActivityAerotec OpsTrifork AITrifork PMYPF
Daily OperationsR/AIII
Alert ResponseRCII
Model UpdatesIR/ACI
Dashboard EnhancementsIRAC
Support EscalationCRAC

Continuous Improvement

ActivityAerotec OpsTrifork AITrifork PMYPF
Accuracy ReviewsCR/AIC
Feature RequestsCCRA
Roadmap PlanningCCR/AC
Quarterly ReviewsCCRA

Escalation Path

LevelScopeContacts
1 - OperationalDay-to-day issuesAerotec RPIC + Trifork PM
2 - TechnicalPlatform/integration issuesTrifork AI Lead + YPF Technical
3 - ProjectScope/timeline issuesAerotec Liaison + Trifork PM + YPF PM
4 - ExecutiveContract/strategic issuesAerotec Exec + Trifork Principal + YPF VP